Network Rail is to begin the formal process of seeking the permanent closure of the Brookside level crossing in Dinas Powys, after concluding it has been unable to find a way to safely reopen it.

The footpath crossing, which links Brookside and Castle Close, has been temporarily closed since 26 June following safety assessments which identified increased risks to users.

Network Rail says it has since carried out a comprehensive Narrative Risk Assessment, considering a number of options which could allow the crossing to reopen safely while supporting current and future train services.

However, the organisation says no suitable solution has been identified and it will now progress an application to formally close the public footpath across the railway and permanently close the crossing.

Network Rail has stressed that the recommendation does not mean a final decision to permanently close Brookside has been made.

A formal process involving the local authority would need to take place before any permanent closure, giving residents and other interested parties an opportunity to have their say.

While that process takes place, Network Rail says it will continue to seek extensions to the existing temporary closure.

Brookside is located on a busy section of the Vale of Glamorgan line. When the emergency closure was announced in June, Network Rail said around 150 trains passed through the area each day, while approximately 217 people used the crossing daily. 

Trains would normally travel through the area at speeds of up to 50mph, while more than 56% of people using the crossing were considered vulnerable, including older people, families with pushchairs and those with reduced mobility.

Network Rail previously described the closure as an emergency measure to protect public safety while longer-term options were considered.

The company says Brookside is its highest-risk level crossing across the Wales and Borders route because of the volume of both rail and pedestrian traffic.

Network Rail representatives will return to Dinas Powys next month to discuss the outcome of the risk assessment and its recommendation with residents.

A public engagement session will be held at Dinas Powys Library and Activity Centre, Fairoaks, The Murch, on Tuesday 8 December, between 2pm and 4pm and again from 5.30pm until 7.30pm.

Do you have a story to share? Email News@broradio.fm 

 

More from Bro Radio Newsroom

Vale Weather

  • Thu

    6°C

  • Fri

    10°C

  • Sat

    11°C

  • Sun

    11°C

  • Mon

    12°C

Local events