Work to rectify fire safety defects and other issues at some high rise apartments in Cardiff Bay will take longer than expected, a major developer has confirmed.
The Local Democracy Reporting Service understands that Redrow initially told leaseholders at the Celestia complex that remediation work on the buildings there would take two years.
Following a tender process, Redrow has now contracted a firm to undertake work on the buildings which it said could now take six months longer than initially planned. However, there are concerns that the work could take even longer than this.
Speaking at the Senedd on Tuesday, South Wales Central MS Rhys ab Owen said: "At the end of October, they [leaseholders] found out in a meeting attended by Welsh Government officials that the remediation work was now going to take two and a half years rather than two years."
"Two days later it had increased to three years. No reason was provided why."
Redrow continues to insist that the current works programme is for 130 weeks, starting next February.
On top of their concerns about fire safety, residents and leaseholders at Celestia who have paid out thousands in service charges over the years previously complained about algae on the side of buildings and chunks of render coming loose and falling off.
There are also calls for Redrow to show leaseholders details about the tender exercise it carried out for the works.
Although a contractor has now been appointed, contractual formalities are still being finalised.
Mr Owen added in the Senedd: “There were three tendering processes for the remediation work at Celestia. Redrow has refused to publish the tendering process."
“Imagine having work at your home. Three firms have tendered for that work and you are not allowed to see the tenders at all. It breeds cynicism. It breeds concern."

Redrow and a number of other developers have signed the Welsh Government’s developer’s contract, committing them to undertake work to address fire safety issues in buildings they have built over the last 30 years.
A Redrow spokesperson said: “Following a thorough selection process, we have appointed a specialist contractor to carry out the remediation, starting in February 2025."
“We are in discussions with the management company over the disruption caused by the scaffolding needed and, depending on the outcome, the project may be six months longer than originally planned but we are committed to completing it as quickly – and with as little impact on residents – as possible.”
Redrow’s offer to fund and undertake works at Celestia in April this year was welcomed by leaseholders, but cladding campaigners in Wales have continued to raised concerns about the progress of remediation works across the country.
Even when Celestia Management Company Limited (CMCL) was under the impression that work to fix the apartment blocks would take two years, they noted that leaseholders would have to endure “years of disruption and being unable to sell”.
Cladding campaigners Welsh Cladiators is calling on the Welsh Government to support leaseholders and ask Redrow to share their tenders for the Celestia works.
Concerns have also been raised about which apartment block will have work carried out on it first.

Vega House, which is the tallest building at Celestia, was described as a “major concern” by CMCL in an email sent to residents in 2019, following conversations with the fire service.
Redrow said Vega House is “being prioratised within the wider programme of works” at Celestia.
A Welsh Government spokesperson said: “We are aware of the updated work schedule proposed at the conclusion of a competitive tender process."
“The tender process considered several factors such as resident safety, quality, and standard of the works, and not just cost."
“We are committed to ensuring the highest standards of building safety in Wales and we are actively engaged with all major developers in Wales on an extensive programme of work to address external and internal fire safety issues.”

Vueling withdraws winter flights to Aicante this winter
Playground in Barry forced to close after fire damages equipment
Campaigners Take Fight for Fairer Pathways in Welsh Women’s Football to Parliament
Vale Councillor Gwyn John Launches His First Novel at Llantwit Major Book Signing
Pink poppy display commences with celebration of life
Former Barry office block converted into new homes for people at risk of homelessness
Welsh Government publishes independent report on Level 4 intervention at Cardiff and Vale UHB
Three CoastSnap stations set to be installed along the Glamorgan Heritage Coast
Daffodil Runner statue installed at Marie Curie Hospice in Penarth
Woman Dies After Incident in Leckwith as Police Investigation Continues
Vale entrepreneur wins national Innovate UK award for sustainable construction technology
Cardiff Airport retains top accessibility rating as regulator reports record demand for assistance
Open Doors event to showcase hidden world of Glamorgan Archives
New details have emerged of a new tree-lined public square that will replace a traffic dominated junction
Dyffryn Gardens’ Edwardian rose garden blooms again after decade-long restoration
Barry’s Own Daniel White to Walk 190 Miles Back to Where His Round Table Story Began
1,300 people attend Flying Start Family Fun Day
Dispersal order put in place to tackle anti-social behaviour
Interim Chief Executive Appointed at Cardiff and Vale University Health Board
Cardiff Theatre Marks 50 Years of Service for Long‑Standing Staff Member